2025-09-16
A 100-day and night effort delivers excellence—Sichuan Host successfully completes the nitrogen supply and pipeline purging tasks for ExxonMobil’s multi-billion-dollar ethylene project.
Recently, Sichuan Host Oil and Gas Technology Co., Ltd. successfully completed the nitrogen supply and process pipeline purging/blow-out operations for ExxonMobil’s Huizhou Ethylene Project. The project, which spanned over 180 days, was smoothly concluded on September 15. This successful delivery not only set three company records—tied for the "longest continuous equipment operation time for a single project," the "largest total liquid nitrogen usage," and the "longest consecutive work duration for personnel on a single project"—but also marked a significant milestone, showcasing the company’s cutting-edge technical capabilities and service excellence at an internationally competitive level. It firmly positions Sichuan Host Oil and Gas Technology as a leader in the high-end energy market, paving the way for future growth and expansion into premium energy sectors.
2025-09-08
1376-Meter Pipeline Pre-Cooling Race: Longkou Nanshan LNG Unloading Pipeline Successfully Completed with Efficient Liquid Nitrogen Pre-Cooling
"Temperature monitoring throughout the unloading system met all standards, and the liquid nitrogen pre-cooling operation was successfully completed!" With the confirmation signal echoing from the central control room at Longkou Nanshan LNG Receiving Station, the liquid nitrogen pre-cooling (experimental cooling) of the station’s Phase I unloading system officially came to a triumphant close on August 25. This project not only served as a critical validation of the receiving station’s core unloading pipelines’ ability to withstand low-temperature conditions but also set a new industry benchmark with its cutting-edge operational efficiency and exceptional quality—laying a solid foundation for the station’s safe and highly efficient subsequent commissioning.
Breaking News | Profit Completion Rate Hits 109%! Nitrogen Business Exceeds Full-Year Target in First Half of the Year
The Phase III Pre-cooling Project at the Xinao Zhoushan LNG Receiving Station Successfully Concludes.
At 11:00 a.m. on July 29, as the control room issued the clear instruction, "The terminal vertex temperature has reached -120°C, and pre-cooling of the low-pressure export main pipeline is complete," the nitrogen pre-cooling operations for the two core pipelines—namely, the unloading main and the low-pressure export main—at the third-phase project of the Sinopec (Zhoushan) LNG Receiving Station successfully concluded across the board! This marks the achievement of a key project milestone to a high standard, removing critical technical hurdles and paving the way for subsequent system startup, commissioning, and safe operation.
Crafting excellence with匠心, overcoming countless challenges through实干 — A record of the completion of the Host Yanting Natural Gas Processing Plant project
The PetroChina Southwest Oil and Gas Field Yanting Natural Gas Processing Plant project is a strategic-level engineering initiative for 2025, spearheaded by Host Oil and Gas Technology Co., Ltd. It plays a critical role in ensuring the stable supply of natural gas to the Sichuan-Chongqing region by providing core equipment for vital commissioning tasks. From February 24 to May 18—spanning 83 grueling days—the team tackled eight major operational modules under some of the most extreme environmental and operational conditions: freezing cold temperatures (with the lowest site temperature dipping as low as 0°C in February), scorching heat (peaking at 35°C from late April through the project’s conclusion), and high-pressure challenges (including XAI helium gas area leak-testing pressures reaching up to 25 MPa). Key tasks included successfully commissioning the thermal oil circulation system, drying eight specialized gas-handling units, and pre-cooling and filling storage tanks of various sizes—all while maintaining precision and efficiency under these demanding circumstances.
2025-04-16
Bringing hearts and minds together to create excellence—overcoming challenges with unwavering commitment—Host provides comprehensive support as the Saltting Natural Gas Processing Plant Pre-Cooling Project kicks off.
Sichuan Host Oil and Gas Technology Co., Ltd. (hereinafter referred to as "Host") has successfully launched the pre-cooling project for the Yanting Natural Gas Processing Plant, which the company undertook. Previously, Host completed critical tasks such as ensuring a stable supply of heat transfer oil for LNG operations, drying the mixed refrigerant system, and preparing the ethylene, propane, and isopentane storage tanks and spherical tanks. With efficient construction management, precise resource allocation, and an impeccable safety record free of incidents, the project team has laid a solid foundation for the plant’s reliable and steady operation moving forward—demonstrating Host’s strong expertise and unwavering commitment to excellence in the oil and gas technology sector.
2025-04-02
Sichuan's Host Equipment Team rose to the challenge, efficiently ensuring the critical milestones of the ExxonMobil project—demonstrating their commitment to service through responsibility and expertise.
On April 2, 2025, at the ExxonMobil project site in Huizhou Daya Bay Economic and Technological Development Zone, Sichuan Host Oil and Gas Technology Co., Ltd.'s equipment maintenance team successfully addressed a series of operational challenges with their rapid response and expert technical skills, ensuring the smooth progress of the project's purging process.