August 28, 2019: Annual Inspection Project for Ball Tanks No. 3 and No. 4 at Deyang Fufeng Storage and Distribution Station
The annual inspection project for spherical tanks No. 3 and No. 4 at the Deyang Fufeng Storage and Distribution Station in 2019 was launched on May 29, with all construction tasks completed by August 5. The station successfully resumed operations on August 27, marking the end of a three-month-long process. Key activities during this period included the erection of internal and external scaffolding for the tanks, anti-corrosion work, nitrogen purging, weld inspections, and necessary repairs.
8.27 The spherical tank was successfully put into operation, and the owner, supervisor, designer, and contractor jointly conducted a technical review. The owner fully acknowledged our company’s strong technical expertise and robust management capabilities. Additionally, Mr. Long, Chairman of Deyang Natural Gas Co., Ltd., specifically expressed his gratitude for our team’s hard work and dedication.